| _2026x_1_12a70364_1789522470201_737876_5617 | 1 | System Level Requirements | — | uncovered |
| _2026x_1_12a70364_1789522470210_613186_5619 | 1.1 | Heater Initialization: The boiler shall heat water to 84°C within 90 seconds of turning on the coffee machine | - satisfy: unresolved link _2026x_1_12a70364_1789524431087_459748_5711
- satisfy: unresolved link _2026x_1_12a70364_1789524431091_435540_5713
- refine: Water Temperature Constraint
- satisfy: Boiler
- verify: Water Heating Analysis Context
| covered |
| _2026x_1_12a70364_1789522470213_487063_5622 | 1.2 | Overheating: The thermostat shall stop all power supply if the instantaneous water heater exceeds 170°C | | covered |
| _2026x_1_12a70364_1789522470217_232543_5625 | 1.3 | Water Tank Level: The water tank will not brew coffee if there is less than 500mL of water | - refine: Refill Water Tank
- satisfy: Water Tank
| covered |
| _2026x_1_12a70364_1789522470220_757311_5628 | 1.4 | Coffee Bean Level: The grinder will not grind coffee beans if there is less than 45g of beans within the bean container | - refine: Refill Coffee Beans
- satisfy: Bean Storage
| covered |
| _2026x_1_12a70364_1789522470227_43173_5631 | 1.5 | Water Tank Capacity: The water tank shall be able to hold a max capacity of 2.4L | | covered |
| _2026x_1_12a70364_1789522470229_653956_5634 | 1.6 | Coffee Bean Capacity: The coffee bean container shall be able to store a max weight of 300g of coffee beans | | covered |
| _2026x_1_12a70364_1789522470232_505575_5637 | 1.7 | Grounds Draw Waste: The grounds draw can store a max waste capacity of 8 grounds before it is deemed full | | covered |
| _2026x_1_12a70364_1789522470236_795679_5640 | 1.8 | Pump Pressure: The pump presser shall not be greater than 15 bar | | covered |
| _2026x_1_12a70364_1789522470238_822356_5643 | 1.9 | System Check: The coffee machine will perform a system check to confirm coffee beans and water levels are satisfied before a coffee is made | - satisfy: Coffee Machine System
- satisfy: Control Module
| covered |
| _2026x_1_12a70364_1789522470240_748943_5646 | 1.10 | System Alert: The coffee machine will alert to user of a system check to be addressed | - satisfy: Coffee Machine System
- satisfy: User Interface Panel
| covered |
| _2026x_1_12a70364_1789522470243_75877_5649 | 1.11 | Control Panel: The coffee machine shall have a digital display which the user can make selections with ease | - satisfy: User Interface Panel
| covered |
| _2026x_1_12a70364_1789522470246_238622_5652 | 2 | Cleaning Requirements | — | uncovered |
| _2026x_1_12a70364_1789522470249_829935_5654 | 2.1 | Clean brewing unit: The maintenance operator shall clean the brewing unit once a week | | covered |
| _2026x_1_12a70364_1789522470251_936773_5657 | 2.2 | Clean Machine Exterior: The maintenance operator shall clean the exterior only using water and kitchen detergent | | covered |
| _2026x_1_12a70364_1789522470252_176734_5660 | 2.3 | Clean Water Tank: The maintenance operator shall clean the water tank 1 time per week | | covered |
| _2026x_1_12a70364_1789522470268_212057_5663 | 3 | Safety Requirements | — | uncovered |
| _2026x_1_12a70364_1789522470269_5755_5665 | 3.1 | Internal Features | — | uncovered |
| _2026x_1_12a70364_1789522470270_589609_5667 | 3.1.1 | Gearmotor Overload: If the gearmotor overloads the motors electronic system shall switchoff after 8-10s and the machine is stopped | — | uncovered |
| _2026x_1_12a70364_1789522470271_475286_5670 | 3.1.2 | HWS Valve Open During Brewing: During brewing operation if the HWS valve is opened the coffee machine shall interrupt the water flow | — | uncovered |
| _2026x_1_12a70364_1789522470272_63721_5673 | 3.1.3 | Interruption By Removal Of Dregs Draw: During operation if interruption occurs by the removal of the dreg draw the machine shall continue its function unrestricted once the drawer is returned | — | uncovered |
| _2026x_1_12a70364_1789522470273_392927_5676 | 3.1.4 | Main Power Supply Disconnection During Operation: If power failure/side doors opened during operation the coffee machines gears will complete the function commenced but without brewing | — | uncovered |
| _2026x_1_12a70364_1789602694801_483599_6108 | 3.1.5 | Electrical Isolation On Dispense: During water dispensing the coffee machine shall electrically isolate the water path and incorporate a residual current device (RCD) so that a short circuit cannot energise the chassis or expose the operator to electric shock. | - satisfy: Power Supply
- satisfy: Dispensing Subsystem
| covered |
| _2026x_1_12a70364_1789522470274_644308_5679 | 3.2 | External Features | — | uncovered |
| _2026x_1_12a70364_1789522470275_767711_5681 | 3.2.1 | Regulatory Compliance Mark: The coffee machine unit shall not be sold unless it has a RCM with the Australian standards of the AS/NZS 4417.1 and AS/NZS 4417.2 | — | uncovered |